Israel risks becoming a pollution haven in the global race to build AI data centers
As the Electricity Authority opens the door to another 1,000MW of data center capacity, the Environmental Protection Ministry warns of rising emissions, health costs and pressure on the country's natural gas reserves.
The Electricity Authority has announced plans to position Israel as a global leader in connecting data centers to the power grid. But a senior official at the Ministry of Environmental Protection is warning of significant consequences. "Air pollutant emissions will rise by more than 10% once data centers with a capacity of 3,000 megawatts are established, causing economic damage through increased morbidity and mortality, lost workdays and other costs," she said.
The ministry estimates that Israel’s rapid push to establish data centers will cause approximately NIS 2 billion in annual economic damage from the additional electricity generation they require, plus more than NIS 1 billion from the operation of backup generators. The anticipated costs also include higher greenhouse gas emissions and faster depletion of Israel’s natural gas reserves. Beyond the financial damage, the ministry warns of an increase in annual deaths caused by air pollution, which is already responsible for an estimated 5,500 premature deaths in Israel each year.
AI is reshaping the global energy landscape, as major technology companies race to build massive data centers around the world. According to the latest forecast from the International Energy Agency (IEA), electricity consumption by data centers is expected to nearly double, from 485 terawatt-hours in 2025 to 950 TWh in 2030, accounting for approximately 3% of global electricity consumption. Over the same period, electricity consumption by data centers dedicated to artificial intelligence is expected to triple. For comparison, 950 TWh is slightly more than Japan’s current annual electricity consumption.
In the United States, data centers are expected to account for nearly half of the projected growth in electricity demand through 2030. Local communities are increasingly bearing the costs of this technological expansion, including higher air pollution from facilities that operate polluting backup generators, consume vast amounts of electricity and require large quantities of water for cooling. Data centers are also affecting electricity prices. According to the Federal Reserve, wholesale electricity prices rose by 6.9% last year, driven in part by demand from these facilities.
Opposition to data center developments is growing in communities around the world, where residents are also concerned about the large tracts of land these facilities occupy. In the United States, the issue even influenced this month's midterm elections. A September poll by Quinnipiac found that nearly three out of four Americans opposed having a data center in their community. During the elections, 41 ballot measures concerning data centers were put to a vote, with voters rejecting the proposed developments in all but one case. In an NBC exit poll, 23% of voters said data centers were a "decisive" factor in their congressional vote, while another 33% described them as a "significant" factor.
The day after the election, Nvidia lost $450 billion in market value. OpenAI has since pledged to use closed-loop cooling systems and to pay for the electricity consumed by its data centers. It has also moved to rebrand its facilities as "computing campuses."
In July, the Electricity Authority froze the processing of grid connection requests for data centers with electricity demands exceeding eight megawatts, after approving 2,000MW of capacity. Developers had submitted requests totaling 27,000MW, roughly three times Israel's current electricity consumption and well above the country's record peak demand.
The authority recently announced plans to release an additional 1,000MW of capacity, potentially enabling the construction of facilities as large as 200MW, a scale not yet seen elsewhere in the world. "Realizing this allocation is expected to result in data centers accounting for approximately 20% of national electricity consumption, positioning Israel among the world's leaders in the integration of data centers relative to total consumption," the Electricity Authority said.
Opening the door to these large facilities is expected to require the construction of at least three new polluting power plants in Israel to meet their electricity needs.
But alongside the potential economic benefits, the expansion carries significant environmental and public-health costs that will ultimately be borne by Israeli residents. The concern is that, at a time when communities in other countries are increasingly resisting data center developments, Israel could become a "backyard" for the sector's pollution.
In a sharply worded letter, Shuli Nazar, Deputy Director General for Environmental Regulation and Risk Prevention at the Ministry of Environmental Protection, warned of a broad range of risks. In addition to increased air pollution and the resulting rise in morbidity and mortality, she said, higher greenhouse gas emissions would make it harder for Israel to meet its climate targets.
According to Nazar, offsetting the additional emissions from data centers would require Israel to set a target of approximately 45% renewable energy by 2035, about 10 percentage points higher than the target recommended by the Electricity Authority. There is considerable skepticism within the energy sector about whether Israel can meet even its existing renewable energy targets.
Nazar also warned that implementing the Electricity Authority's plan would accelerate the depletion of Israel's domestic natural gas reserves and shorten their expected lifespan.
"At the projected consumption rate, the reserves will be exhausted within approximately 17 years, about three years earlier than anticipated," she wrote. "In this scenario, the use of polluting fuels is expected to increase, creating an unreasonable need for the extensive operation of old, polluting coal-fired units, steam-based power plants and generators near urban areas."
Nazar called on the Electricity Authority to address these risks by, among other measures, accelerating the integration of renewable energy and requiring data centers to use clean electricity from the outset. She also advocated setting a net-zero emissions target for data centers and introducing a differential electricity tariff to encourage them to consume cleaner power, given the substantial additional demand they are expected to place on the grid.
"Current partial regulation risks locking in long-term environmental and economic consequences. The power plants built to supply this electricity will remain in operation for decades. Rectifying the situation later would be far more complex and costly than establishing the right policy now," Nazar concluded.